Official: Bayern to expand Unterhaching stadium for women's team, capacity to reach 15,000
Live StreamsLive scoresTV GuideTop picksOdds
On November 27, Bayern officially announced that the club will launch the first phase of the Sportpark Unterhaching redevelopment project and plans to submit the building application for the initial phase before the end of the year. Once completed, the sports park will feature a 15,000-capacity stadium, with the entire project set to be carried out in phases over the coming years. Upon completion, the stadium will also become the new permanent home of Bayern München Women.

In December 2025, Bayern acquired the Sportpark Unterhaching, which covers an area of approximately 45,000 square meters, through its subsidiary Allianz Arena München Stadion GmbH. On November 26, Bayern CEO Jan-Christian Dreesen, Allianz Arena GmbH managing director Jürgen Muth, and the club's women's football director Bianca Rech, accompanied by Unterhaching mayor Korbinian Rausch, held a press conference at the sports park's VIP building to unveil the project's plans.
Dreesen said: "Sportpark Unterhaching is an important part of our future development plans. Through this special infrastructure project, we are investing in the development of women's football and firmly believe this will help us establish ourselves among Europe's elite."
Rech said: "For our players, Sportpark Unterhaching is not just a new home, but a space to grow. Here, the future of Bayern München Women will gradually take shape and set a benchmark across Europe. Every stand and every training pitch reflects Bayern München Women's determination to keep progressing. We are really looking forward to it."

Following that, Allianz Arena GmbH managing director Muth outlined the specific construction schedule.
After acquiring the sports park, Bayern initially focused on infrastructure investments to ensure the stadium met UEFA's operational requirements. As a result, starting this season, Bayern München Women have already been able to play their Women's Champions League home matches at Sportpark Unterhaching. Their final league-phase match of this season's Women's Champions League will take place on December 16 against defending champions Barcelona Women.
Over the past few months, the club has further finalized the specific construction plans for each phase. The relevant work will proceed gradually starting in spring 2027, while ensuring that matches for both Bayern München Women and SpVgg Unterhaching's first team can continue normally and that minimum stadium capacity requirements for all competitions are met.
Phase 1: Redeveloping the North Stand and building the FC Bayern Frauen Campus
The first building application covers the northern area of the sports park. Like the rest of the stadium, the North Stand will be fitted with a roof and is expected to be ready for use in the 2028-29 season.
At the same time, the FC Bayern Frauen Campus located in the northern area will also be a core component of the project. The center will house all of the club's women's teams from the senior squad to the youth academy and is expected to be completed in the summer of 2029, when Germany will also host the Women's Euro.
Phase 2: Redeveloping the West Area and upgrading training pitches
Once the North Stand and the women's training center are operational, the club will begin construction work on the western area.
At that stage, training facilities will also be a key focus of the redevelopment, particularly Pitch 1, which will be converted from artificial turf to natural grass to further improve the team's training conditions.
Phase 3: Completing redevelopment of the South and East Areas
The final phase of the project will redevelop the southern and eastern areas of the sports park. Once all work is completed, Sportpark Unterhaching will become a brand-new 15,000-capacity stadium and serve as an important future home for Bayern München Women.